Formwork and concreting work
2020-2022
- Client :
- Hydro-Quebec
- Lieux :
- Romaine 4 hydroelectric complex
Work executed
- Formwork and concreting work
- Removal of wire mesh
- Preparation and cleaning of foundation surfaces
- Installation of steel structure
- Architecture and plant envelope
- Roof and precast concrete panels
- MALT
- Assembly and testing of the main crane
- Excavation work
- Concreting and injection of armored pipes
- Construction services (water supply, dewatering, lighting, heating, and electricity)
Constraints
- Very significant health and safety issues on this specific project
- Winter conditions
- Significant co-activity with third parties
- Subcontractor management